ANNEX 13
SUMMARY OF BUDGETS AND ANNEXES
Annex Description |
2021/22 £K |
||
Performance Review of maintenance capital delivery 20/21 |
9,027
|
||
Review of the City of York Council 2020/21 Capital Highways Programme |
Annual programme performance completion |
||
Carriageway resurfacing |
Progress |
% |
|
Brecks Lane |
Completed |
|
|
Link Road, New Earswick |
Completed |
|
|
Gale Lane |
Completed |
|
|
Thanet Road |
Completed |
|
|
West Thorpe |
Completed |
|
|
Foxwood Lane |
Completed |
|
|
Scarcroft Road |
Completed |
||
Cemetery Lane |
Completed |
|
|
Wheldrake Lane haunching |
Completed |
|
|
Kent Street |
In progress |
Delayed due to essential Drainage Works being required. Aiming to start works mid 2022 subject to road space booking approvals. Carried forward to 22/23 |
|
Elvington Lane from Riverside gdns to Bridge |
Completed |
||
Osbaldwick Village |
Completed |
|
|
Marygate |
In progress |
Linked to Marygate Footways scheme. Design Works underway, planned to start in March 2022 |
|
Grange Street |
Completed |
|
|
Bishopthorpe Road |
Deferred to 2022/23 |
EA Flood Defence works in the area and opportunity to combine with other works in the area |
|
Footway |
Progress |
% |
|
Southdown Road |
Completed |
|
|
Forestgate |
Completed |
||
Jasmine Close |
Completed |
In progress on site – completed by 24th December 2021 |
|
Auster Road |
Completed |
|
|
Burton Stone Lane |
Completed |
|
|
St Nicholas Crescent |
Completed |
|
|
Beckfield Lane from Boroughbridge Rd to Norman Drive |
In progress |
Drainage design underway to be completed prior to footway works being undertaken. Carried forward to 22/23 |
|
Hamilton Drive |
Not complete |
Carried forward to 22/23 to align with another planned footway project on this street to reduce impact – to be completed in summer school holidays |
|
Greengales Lane |
In progress |
Drainage design underway to resolve prior to footway works being undertaken. |
|
High Oaks |
In progress |
Scheduled to commence on 14th February 2022 for 2 weeks work |
|
Colliergate |
In progress |
Scheduled to commence on 3rd January 2022 |
|
Church Street |
In progress |
Scheduled to commence on 3rd January 2022 |
|
Hyrst Grove |
Completed |
|
|
Melbourne Street |
Completed |
||
Lendal |
Not complete |
Carried forward to 22/23 to reduce impact on city centre |
|
East Mount Road |
In progress |
Scheduled to commence on 7th February 2022 |
|
Coppergate from 3 Tuns to Low Ousegate |
Not complete |
Carried forward to 22/23 to reduce impact on city centre |
|
Blake Street |
Not complete |
Carried forward to 22/23 to reduce impact on city centre |
|
Marygate |
In progress |
Linked to Marygate Carriageway scheme. Design Works underway, planned to start in March 2022 |
|
Pre-patching and Surface Dressing |
Progress |
% |
|
Towthorpe Moor Lane from Strensall Road to waste site |
In progress |
Most work complete, Scheme to be completed 22/23 |
|
A1079, Hull Road, Dual Carriageway Section |
In progress |
Drainage issues to resolve, scheme to be completed 22/23 |
|
Holtby lane |
In progress |
Most work complete, Scheme to be completed 22/23 |
|
Large Patching |
Progress |
% |
|
Kestrel Wood Way |
Completed |
|
|
Penine Close |
Completed |
|
|
Eastholme Drive |
Completed |
|
|
Haxby Road, from 171-181 (Hambleton Terrace) |
Completed |
|
|
Highcliffe Court |
Completed |
|
|
Bradley Lane |
Completed |
|
|
Main Street, Copmanthorpe |
Completed |
|
|
Askham Lane, A1237 |
Completed |
|
|
Atterwith Lane, Hessay |
Completed |
|
|
The Green, Acomb |
Completed |
|
|
Greengales Lane |
Completed |
|
|
Straylands Grove |
Completed |
|
|
Micklegate / Skeldergate TSAR |
Completed |
|
|
Wheldrake Lane, Golf Course |
Completed |
|
|
St Oswalds Road |
Completed |
|
|
Elvington Lane, Clockhouse Bend |
Completed |
|
|
Lendal |
Completed |
|
|
Micro Patching |
Progress |
% |
|
Lowick |
Completed |
|
|
Troutbeck |
Completed |
|
|
Woodthorpe School Entrance |
Completed |
|
|
Overdale |
Completed |
|
|
Glenridding |
Completed |
|
|
Windermere |
Completed |
|
|
Brambledene |
Completed |
|
|
Dringfield Close |
Completed |
|
|
Wains Road |
Completed |
|
|
Lockwood Street |
Completed |
|
|
Unallocated funding from 20/21 programme (provision from DfT above assumed level) |
Progress |
|
|
Haxby station |
Completed |
|
|
Hostile Vehicle Measures |
In progress |
|
|
Various Highways repairs (inc. cycle margins, road joint repair, speed cushions) |
In progress |
|
|
Danesgate |
In progress |
|
|
Street lighting safety improvements |
In progress |
|
|
Unadopted road condition surveys |
In progress |
To be added to this year condition survey, followed by a delivery programme and a bid for the Council capital fund for 2023-2024 financial year to do the resurfacing. |
|
|
|
|