ANNEX 13

 

SUMMARY OF BUDGETS AND ANNEXES

 

Annex Description

2021/22

£K

Performance Review of maintenance capital delivery 20/21

9,027

 

Review of the City of York Council 2020/21 Capital Highways  Programme 

Annual programme  performance completion

Carriageway resurfacing

Progress

%

Brecks Lane

Completed

 

Link Road, New Earswick

Completed

 

Gale Lane

Completed

 

Thanet Road

Completed

 

West Thorpe

Completed

 

Foxwood Lane

Completed

 

Scarcroft Road

Completed

Cemetery Lane

Completed

 

Wheldrake Lane haunching

Completed

 

Kent Street

In progress

Delayed due to essential Drainage Works being required. Aiming to start works mid 2022 subject to road space booking approvals. Carried forward to 22/23

Elvington Lane from Riverside gdns to Bridge

Completed

Osbaldwick Village

Completed

 

Marygate

In progress

Linked to Marygate Footways scheme. Design Works underway, planned to start in March 2022

Grange Street

Completed

 

Bishopthorpe Road

Deferred to 2022/23

EA Flood Defence works in the area and opportunity to combine with other works in the area

Footway

Progress

%

Southdown Road

Completed

 

Forestgate

Completed

Jasmine Close

Completed

In progress on site – completed by 24th December 2021

Auster Road

Completed

 

Burton Stone Lane

Completed

 

St Nicholas Crescent

Completed

 

Beckfield Lane from Boroughbridge Rd to Norman Drive

In progress

Drainage design underway to be completed prior to footway works being undertaken. Carried forward to 22/23

Hamilton Drive

Not complete

Carried forward to 22/23 to align with another planned footway project on this street to reduce impact – to be completed in summer school holidays

Greengales Lane

In progress

Drainage design underway to resolve prior to footway works being undertaken.

High Oaks

In progress

Scheduled to commence on 14th February 2022 for 2 weeks work

Colliergate

In progress

Scheduled to commence on 3rd January 2022

Church Street

In progress

Scheduled to commence on 3rd January 2022

Hyrst Grove

Completed

 

Melbourne Street

Completed

Lendal

Not complete

Carried forward to 22/23 to reduce impact on city centre

East Mount Road

In progress

Scheduled to commence on 7th February 2022

Coppergate from 3 Tuns to Low Ousegate

Not complete

Carried forward to 22/23 to reduce impact on city centre

Blake Street

Not complete

Carried forward to 22/23 to reduce impact on city centre

Marygate

In progress

Linked to Marygate Carriageway scheme. Design Works underway, planned to start in March 2022

Pre-patching and Surface Dressing

Progress

%

Towthorpe Moor Lane from Strensall Road to waste site

In progress

Most work complete, Scheme to be completed 22/23

A1079, Hull Road, Dual Carriageway Section

In progress

Drainage issues to resolve, scheme to be completed 22/23

Holtby lane

In progress

Most work complete, Scheme to be completed 22/23

Large Patching

Progress

%

Kestrel Wood Way

Completed

 

Penine Close

Completed

 

Eastholme Drive

Completed

 

Haxby Road, from 171-181 (Hambleton Terrace)

Completed

 

Highcliffe Court

Completed

 

Bradley Lane

Completed

 

Main Street, Copmanthorpe

Completed

 

Askham Lane, A1237

Completed

 

Atterwith Lane, Hessay

Completed

 

The Green, Acomb

Completed

 

Greengales Lane

Completed

 

Straylands Grove

Completed

 

Micklegate / Skeldergate TSAR

Completed

 

Wheldrake Lane, Golf Course

Completed

 

St Oswalds Road

Completed

 

Elvington Lane, Clockhouse Bend

Completed

 

Lendal

Completed

 

Micro Patching

Progress

%

Lowick

Completed

 

Troutbeck

Completed

 

Woodthorpe School Entrance

Completed

 

Overdale

Completed

 

Glenridding

Completed

 

Windermere

Completed

 

Brambledene

Completed

 

Dringfield Close

Completed

 

Wains Road

Completed

 

Lockwood Street

Completed

 

Unallocated funding from 20/21 programme (provision from DfT above assumed level)

Progress

 

Haxby station

Completed

 

Hostile Vehicle Measures

In progress

 

Various Highways repairs (inc. cycle margins, road joint repair, speed cushions)

In progress

 

Danesgate

In progress

 

Street lighting safety improvements

In progress

 

Unadopted road condition surveys

In progress

To be added to this year condition survey, followed by a delivery programme and a bid for the Council capital fund for 2023-2024 financial year to do the resurfacing.